AWE Aldermaston - Enriched Uranium Handling Facility (Pegasus, 09/02396/COMIND), Reserved matters 10/01465/COND1

Date: 
14 June, 2010
Source: 
http://publicaccess.westberks.gov.uk

Application for approval of details reserved by condition 10 drainage strategy - Thames Water condition 11 programme of demolition and condition 14  water supply infrastructure of planning permission reference 09/02396/COMIND
 
Received 14/06/10

Newbury Weekly News - Anti-nuclear group slams uranium store

Date: 
13 February, 2010
Source: 
http://www.newburytoday.co.uk

Newbury Weekly News source
 
The group has said it has now given them added justification for a protest at AWE Aldermaston
 
AN anti-nuclear group has slammed the recent approval of an enriched uranium store at the Atomic Weapons Establishment, Aldermaston.
 

Eastern Area Planning Committee - Reports, Pegasus (09/02396/COMIND)

Date: 
7 February, 2010
Source: 
http://www.westberks.gov.uk

Extract from Planning Report:

NIS - 61% say no to Pegasus development!

Date: 
22 January, 2010
Source: 
http://nuclearinfo.org

NIS source
 
A street survey conducted by local environmental groups shows that a large majority of local people think that the proposed new Enriched Uranium Facility at the Atomic Weapons Establishment (AWE) Aldermaston should not be built.

AWE Aldermaston - Enriched Uranium Handling Facility (Pegasus): 09/02396/COMIND, Consultation response

Date: 
21 January, 2010
Source: 
http://planning.westberks.gov.uk

Consultation response for application 09/02396/COMIND:
 

NAG - NAG objection to Pegasus

Date: 
5 January, 2010
Source: 
http://www.nuclearawarenessgroup.org.uk

Ministry of Defence proposals to build a new Enriched Uranium Facility at the Atomic Weapons Establishment (AWE) Aldermaston could pose potential hazards to the public from a radioactive fire or a critical release of radiation – but NAG considers that not enough information about the development has been provided to enable these risks to be properly evaluated.

Commons Hansard - Ainsworth: Column 1214W

Date: 
16 December, 2009
Source: 
http://www.publications.parliament.uk

Hansard source - 16 Dec 2009 : Column 1214W
Angus Robertson: To ask the Secretary of State for Defence what assessment was made in the best practical environmental options selection study for the Enriched Uranium Project of the merits of the purchase from the US of enriched uranium components for (a) the naval nuclear propulsion programme and (b) the nuclear warhead programme. [305748]

AWE - AWE Submits planning application for Pegasus

Date: 
13 December, 2009
Source: 
http://www.awe.co.uk

AWE source
 
AWE has submitted plans to West Berkshire Council for a replacement facility for the storage and handling of enriched uranium close to the centre of its Aldermaston site.

Commons Hansard - Davies: Column 364W

Date: 
9 December, 2009
Source: 
http://www.publications.parliament.uk

Hansard source - 9 Dec 2009 : Column 364W
Mr. Dai Davies: To ask the Secretary of State for Defence what progress has been made on preparations for Project Pegasus at AWE Aldermaston. [304681]

Commons Hansard - Davies: Column 365W

Date: 
9 December, 2009
Source: 
http://www.publications.parliament.uk

Hansard source - 9 Dec 2009 : Column 365W
Nick Harvey: To ask the Secretary of State for Defence what estimate he has made of the length of the construction period for the new enriched uranium facility at AWE Aldermaston as proposed in the planning application made to West Berkshire council; what plans he has for the usage of the uranium processed there; and if he will make a statement. [305195]